Site Improvement Project Request

SUBMIT YOUR REQUEST BEFORE YOU COMMIT TO A PROJECT

SUBMIT YOUR REQUEST BEFORE YOU COMMIT TO A PROJECT

Contact Carlos Chicas, Executive Director MOT with any questions 


51-day average completion for all Site Improvement Projects Requests (SIPR)

 

NOTE: Projects requiring the Construction Department for Public bidding, Architectural, ADA, DSA, Fire and Life Safety review, etc. could require a year to plan and include additional soft costs
 
AR 3.13 Volunteer Projects: School construction or site improvement
      • To establish guidelines and procedures for projects which relate to school
        construction or site improvements or any physical plant modifications not
        accomplished by the District’s Support Services Division.
      • To eliminate the possibility of misunderstandings among members of the
        community and school support clubs/organizations who wish to provide donations through services or materials to enhance our schools.
         
 
Timelines (estimated completion - 150 days):
Initial review: 30 days
      • Each request submitted to M&O takes 30 days to review. Schedule site walks with M&O early in the planning stages
      • In that review period, a preliminary budget is provided by the site administrator for review
Solicit hard quotes: 30 days
      • If the preliminary budget is approved, M&O will solicit hard bids from Board approved vendors, and then those bids are provided for the site to review and approve
Approvals and Purchase Requisition (PR) coordination: 10 days
      • Once approved, M&O coordinates the PR with the site, the Purchasing Department, the vendor, and any other Departments as needed
Purchasing Department Coordination: 15-30 days
      • As these projects are site funded, they cannot be scheduled until the vendor has the Purchase Order (PO) in hand
Project Completion: 5-20 days
      • Once the project is approved and scheduled, the actual work, depending on the scope, can take another week to four weeks. M&O coordinates the supervision of the project and provides updates along the way to the site as needed
Closeout: 30 days
      • Lastly, M&O inspects the work and assures any punch list items have been addressed, then approves the invoice for payment